Low Catton Road closure and installation of zebra crossing on Main Street

Low Catton Road will be closed from 15 February for 12 days to allow for drainage and carriageway repairs. The Public Notice and map showing the alternative route are attached.

ERYC have advised that work on the installation of the proposed zebra crossing in Main Street is programmed to start week commencing 1 March.  The work will be carried out by the Council's Streetscene services and is expected to take 2 weeks to complete (weather permitting).  The traffic management will be 2-way traffic signals.